Fiscal Year 2020
(Published 7/10/2019)
Month BMR Online & BMR
Import Template
CUTOFF - NOON
Paper Entry &
File Transfer
CUTOFF - 5:00
Online Entry
CUTOFF - Noon
Anticipated
Availability of
Online Level Reports
July NA August 1 August 5 August 7
August NA September 3 September 5 September 7
September NA October 1 October 3 October 5
October 30 November 1 November 5 November 7
November November 28 December 2 December 4 December 6
December December 19 January 2 January 6 January 8
January January 30 February 3 February 5 February 7
February February 27 March 2 March 4 March 6
March March 30 April 1 April 3 April 7
April April 29 May 1 May 5 May 7
May May 28 June 1 June 3 June 5
June TO BE DETERMINED TO BE DETERMINED TO BE DETERMINED TO BE DETERMINED