Fiscal Year 2019
(Revised 11/12/2018)
Month BMR Online & BMR
Import Template
CUTOFF - NOON
Paper Entry &
File Transfer
CUTOFF - 5:00
Online Entry
CUTOFF - Noon
Anticipated
Availability of
Online Level Reports
July NA August 1 August 3 August 7
August NA September 4 September 6 September 8
September NA October 1 October 3 October 5
October -- November 1 November 5 November 7
November November 29 December 3 December 5 December 7
December December 20 January 2 January 4 January 8
January January 30 February 1 February 5 February 7
February February 27 March 1 March 5 March 7
March March 28 April 1 April 3 April 5
April April 29 May 1 May 3 May 7
May May 30 June 3 June 5 June 7
June TO BE DETERMINED - - -